entre views!


first floor framing is pretty much complete-aside from change order no. 001 (see following post), and the dining room ceiling.


view towards new kitchen...low wall is where island will be


view from kitchen to living room


view back towards entrance foyer...new bathroom door to the right


we have salvaged the existing duct risers that supply the second floor- the hvac contractor suggested reusing them to save money and materials!  nice.

oops! forgot to mention.  the plumber started work yesterday and ripped out all of the existing plumbing...all of it, toilets too!  :|
he will be back next week to install the new rough plumbing (and hopefully a toilet!)