not in bad shape, we will remove the wrought iron handrail, expand the size of the foyer---and remove that wallpaper!
More Wallpaper!
We will replace all electrical devices
Study/Den:
We will remove the train wallpaper, replace the trim and add crown moulding and possibly a 12-lite door.
Existing Kitchen/ Future Bath:
This tiny kitchen will turn into a new full bath- the kitchen will be relocated.
View from Entrance:
At the far wall, there will be a set of french doors opening to a new deck. This will be the view as you enter (minus a few walls)
Entrance:
Walls will be removed to open up the entrance and create a foyer instead of a narrow hall
Dining/ Future Kitchen:
The kitchen will be relocated towards the back of the house- in the current location of the dining area.
Basement:
paint, windows, lighting, dri-core flooring...
This tiny kitchen will turn into a new full bath- the kitchen will be relocated.
View from Entrance:
At the far wall, there will be a set of french doors opening to a new deck. This will be the view as you enter (minus a few walls)
Entrance:
Walls will be removed to open up the entrance and create a foyer instead of a narrow hall
Dining/ Future Kitchen:
The kitchen will be relocated towards the back of the house- in the current location of the dining area.
Sunroom/ Future Dining Room:
The plan is to remove the existing flat ceiling and replace it with a cathedral ceiling- install cork flooring- replace the paneling with drywall...
Bedrooms:
The bedrooms are decent- we will replace the windows, add crown moulding and new base, repaint...
Second Floor Bath:
A gut renovation is the only option here! We are also going to expand the size of the bathroom by about 3'.
First Floor Half Bath:
We are going to relocate the first floor bathroom and expand it into a full bath. This space is going to be given over to a larger entry foyer.
The plan is to remove the existing flat ceiling and replace it with a cathedral ceiling- install cork flooring- replace the paneling with drywall...
Bedrooms:
The bedrooms are decent- we will replace the windows, add crown moulding and new base, repaint...
Second Floor Bath:
A gut renovation is the only option here! We are also going to expand the size of the bathroom by about 3'.
First Floor Half Bath:
We are going to relocate the first floor bathroom and expand it into a full bath. This space is going to be given over to a larger entry foyer.
Basement:
paint, windows, lighting, dri-core flooring...